Weekend Road Report, July 9-10, 2022
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
33RD ST W ROAD CLOSED FROM AVE B N TO AVE C N
(Connection repair)
Start: July 9, 8:00 a.m. End: July 10, 4:30 p.m.
TAYLOR ST E WB CURB & CENTER LANES CLOSED FROM HERITAGE WAY TO MCKERCHER DR
(Catch basin replacement)
Start: July 9, 8:00 a.m. End: July 10, 5:00 p.m.
SPADINA CRES EROAD CLOSURE FROM 3RD AVE S TO 20TH ST E
(Taste of Saskatchewan)
Spadina Cr NB Bike Lane closed from 20th to 21st streets.
Start: July 9, 8:00 a.m. End: July 19, 6:00 p.m.
IDYLWYLD DR N NB LEFT TURN LANES CLOSED FROM 60TH ST E TO MARQUIS DR E
(Roadway paving)
NB Left Turns to Marquis Drive will be maintained. 71st Street will be available for Left Turns.
Start: July 9, 5:00 p.m. End: July 10, 7:00 a.m.
8TH ST E EB & WB CURB LANES CLOSED AT ACADIA DR
(Streetlight pole replacement)
Start: July 10, 4:00 a.m. End: July 10, 1:00 p.m.
COLLEGE DR WB OFFRAMP CLOSED FROM COLLEGE DR TO MCKERCHER DR
(Streetlight pole replacement)
Start: July 10, 6:00 a.m. End: July 10, 12:00 p.m.
CLARENCE AVE N NB LANES CLOSED FROM OSLER ST TO COLLEGE DR
(Roadway patching)
Two-way traffic will be maintained in the SB lanes
Start: July 10, 7:00 a.m. End: July 10, 3:00 p.m.
TAYLOR ST E EB RIGHT TURN BAY CLOSED AT KINGSMERE BLVD
(Roadway patching)
Start: July 10, 7:00 a.m. End: July 10, 3:00 p.m.
33RD ST E EB LANES CLOSED AT QUEBEC AVE
(Roadwork)
Start: July 10, 7:00 a.m. End: July 10, 3:00 p.m.
1ST AVE N ROAD CLOSED FROM 22ND ST E TO 23RD ST E
(Roadway patching)
Start: July 10, 7:00 a.m. End: July 10, 3:00 p.m.
1ST AVE N INTERSECTION CLOSED AT QUEEN ST
(Hydrant repair)
Start: July 10, 8:00 a.m. End: July 11, 5:00 p.m.
8TH ST E NB LEFT TURN LANE; & EB CURB & CENTER LANES CLOSED AT MCKERCHER DR
(Valve repair)
Start: July 10, 9:00 a.m. End: July 10, 2:00 p.m.
WANUSKEWIN RD SB LANES CLOSED FROM 71ST ST E TO MARQUIS DR E
(Roadway patching)
Two-way traffic will be maintained in the NB lanes.
Start: July 10, 9:00 a.m. End: July 10, 3:00 p.m.
OVERNIGHT
IDYLWYLD DR N NB MEDIAN LANE CLOSED FROM 51ST ST E TO MARQUIS DR E
(Roadway resurfacing)
Closure will be set nightly and picked each morning.
Start: July 10, 7:00 p.m. End: July 12, 7:00 a.m.
CIRCLE DR E NB & SB MEDIAN LANES CLOSED FROM 108TH ST W TO ATTRIDGE DR
(Bridge deck rehabilitation)
Start: July 10, 7:00 p.m. End: July 13, 7:00 a.m.
ONGOING
IDYLWYLD DR N NB CURB LANE CLOSED FROM 51ST ST E TO MARQUIS DR E
(Roadway resurfacing)
Closures will be set each night and removed the following morning.
Start: July 6, 6:30 p.m. End: July 9, 7:00 a.m.
33RD ST E EB LEFT TURN LANE CLOSED AT WARMAN RD
(Construction)
Start: July 8, 9:00 a.m. End: July 9, 5:00 p.m.
WARMAN RD NB MEDIAN LANE CLOSED FROM LAURISTON ST TO 34TH ST E
(Intersection improvements)
Start: July 8, 9:00 a.m. End: July 9, 5:00 p.m.
2ND AVE ROAD CLOSED FROM 20TH ST E TO 23RD ST E
(Downtown Sidewalk Sale)
Intersection at 2nd Avenue and 22nd Street will remain open
Start: July 7, 5:30 a.m. End: July 9, 7:00 p.m.
CIRCLE DR E EB & WB MEDIAN LANES CLOSED FROM QUEBEC AVE TO VENTURE CRES
(Concrete replacement)
Start: July 5, 7:00 a.m. End: July 10, 5:00 p.m.
CLARENCE AVE S INTERSECTION CLOSED AT BUTE ST
(Construction)
Start: June 23, 7:00 a.m. End: July 11, 5:00 p.m.
1ST AVE N NB PARKING LANE & SIDEWALK CLOSED FROM 23RD ST E TO 24TH ST E
(Cable work)
Start: July 4, 8:00 a.m. End: July 13, 4:30 p.m.
WARMAN RD SB CURB LANE CLOSED AT 33RD ST E
(Intersection improvements)
Start: June 23, 7:00 a.m. End: July 14, 5:00 p.m.
33RD ST E WB CURB LANE CLOSED AT WARMAN RD
(Intersection improvements)
Start: June 23, 7:00 a.m. End: July 14, 5:00 p.m.
ATTRIDGE DR EB & WB MEDAIN LANES CLOSED AT CIRCLE DR E
(Overpass rehabilitation)
Start: July 5, 8:00 p.m. End: July 16, 7:30 p.m.
DUNDONALD AVE SB CURB LANE CLOSED FROM 11TH ST W TO CAEN ST
(Drainage improvements)
Start: June 28, 7:00 a.m. End: July 25, 4:30 p.m.
3RD AVE N ROAD CLOSED FROM 25TH ST TO QUEEN ST
(Water main repair)
Start: June 14, 7:00 a.m. End: July 29, 5:00 p.m.
MCORMOND DR ROAD CLOSED AT BRIGHTON BLVD
(New road construction)
Start: June 29, 7:00 a.m. End: August 8, 5:00 p.m.
RUTH ST E INTERSECTION CLOSED AT CAIRNS AVE
(Water main replacement)
Start: June 29, 7:00 a.m. End: August 22, 5:00 p.m
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.