Weekend Road Report, August 6-7, 2022
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
CIRCLE DR E WB MEDIAN LANE CLOSED FROM SPADINA CRES E TO MILLAR AVE
(Permanent line markings)
Start: August 6, 7:00 p.m. End: August 7, 5:00 a.m.
CIRCLE DR E EB CURB & CENTER LANES CLOSED FROM 1ST AVE N TO MILLAR AVE
(Sewer lining)
Start: August 6, 8:00 p.m. End: August 7, 6:00 a.m.
51ST ST E EB MEDIAN & CENTER LANES CLOSED FROM CLEVELAND AVE TO MILLAR AVE
(Hydro vac valve)
Start: August 7, 8:00 a.m. End: August 7, 12:00 p.m.
TAYLOR ST E INTERSECTION CLOSED AT WIGGINS AVE S
(Water main repair)
Start: August 7, 8:00 a.m. End: August 8, 4:30 p.m.
OVERNIGHT
CIRCLE DR E WB CURB LANE CLOSED FROM SPADINA CRES E TO WARMAN RD
(Line painting)
Start: August 7, 7:00 p.m. End: August 8, 5:00 a.m.
ONGOING
CLARENCE AVE S NB & SB MEDIAN LANES FROM 8TH ST E TO COLONY ST
(Durable Markings)
Start: August 5, 7:00 p.m. End: August 6, 5:00 a.m.
CIRCLE DR E EB CURB & CENTER LANES FROM VENTURE CRES TO MILLAR AVE
(Sewer lining)
Start: August 5, 8:00 p.m. End: August 6, 6:00 a.m.
2ND AVE N NB & SB LEFT TURN LANES CLOSED FROM 25TH ST E TO QUEEN ST
(Sewer lining)
Start: August 5, 8:00 p.m. End: August 6, 6:00 a.m.
4TH AVE N ROAD CLOSED FROM 22ND ST E TO 24TH ST E
(Food Truck Wars)
Start: August 3, 7:00 a.m. End: August 7, 5:00 p.m.
DIEFENBAKER DR NB DRIVING LANE, PARKING LANE & SIDEWALK CLOSED FROM LAURIER DR TO DOUGLAS CRES
(Sidewalk repair)
Start: August 2, 7:00 a.m. End: August 7, 5:00 p.m.
MCORMOND DR ROAD CLOSED AT BRIGHTON BLVD
(New road construction)
Start: June 6, 7:00 a.m. End: August 8, 5:00 p.m.
7TH AVE N VARIOUS PARKING LANES, & SIDEWALKS CLOSED AT BALMORAL ST
(Pedestrian ramp replacements)
Start: August 2, 7:00 a.m. End: August 11, 4:30 p.m.
CIRCLE DR E WB CURB LANE CLOSED FROM MILLAR AVE TO 1ST AVE N
(Roadway paving)
Start: August 2, 7:00 a.m. End: August 12, 6:00 p.m.
4TH AVE N ROAD CLOSED FROM 25TH ST E TO QUEEN ST
(Water main construction)
Start: July 22, 7:00 a.m. End: August 19, 5:00 p.m.
25TH ST E EB LANES CLOSED FROM 5TH AVE N TO SPADINA CRES E
(Water main replacement)
Start: August 3, 7:00 a.m. End: August 20, 5:00 p.m.
RUTH ST E INTERSECTION CLOSED AT CAIRNS AVE
(Water main replacement)
Start: June 29, 7:00 a.m. End: August 22, 5:00 p.m.
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.