NEW
IDYLWYLD CRES NB LANES CLOSED FROM 11TH ST W TO SASKATCHEWAN CRES W
(Sewer lining)
Start: February 21, 9:00 a.m. End: February 21, 3:00 p.m.
8TH ST E EB CURB LANE CLOSED FROM CAIRNS AVE TO WIGGINS AVE S
(Sanitary main)
Start: February 21, 9:00 a.m. End: February 21, 3:00 p.m.
8TH ST E WB MEDIAN LANE AND EB LEFT TURN LANE CLOSED FROM CAMPBELL AVE TO EMERSON AVE
(Traffic signal cable replacement)
Start: February 21, 9:00 a.m. End: February 21, 3:00 p.m.
ONGOING
CIRCLE DR S EB CURB LANE CLOSED FROM LORNE AVE TO CLARENCE AVE S
(Construction)
Start: February 20, 8:00 a.m. End: February 22, 5:00 p.m.
BRIGHTON BLVD ROAD CLOSED FROM TASKAMANWA ST TO 8TH ST E
(Construction)
Use McOrmond Dr
Start: November 20, 2023, 7:00 a.m. End: November 18, 2024, 5:00 p.m.