Daily Road Report - August 23, 2023
*This report includes road restrictions on Priority 1 (high traffic, high speed) streets only.
NEW
3RD AVE N ROAD CLOSED FROM 26TH ST E TO QUEEN ST
(Roadway patching)
Start: August 23, 7:00 a.m. End: August 23, 3:00 p.m.
IDYLWYLD DR N NB SPEED REDUCTION FROM 60TH ST E TO 64TH ST E
(Streetlight replacements)
Start: August 23, 9:00 a.m. End: August 23, 3:00 p.m.
NIGHTWORK
CIRCLE DR W SB MEDIAN LANE CLOSED FROM LAURIER DR TO 22ND ST W
(Crash cushion repairs)
Start: August 23, 7:00 p.m. End: August 24, 6:00 a.m.
CIRCLE DR S EB & WB MEDIAN & CENTRE LANES CLOSED FROM DIEFENBAKER PARK RD TO SPADINA CRES W
(Bridge washing & sealing)
Start: August 23, 8:00 p.m. End: August 24, 6:00 a.m.
CIRCLE DR S EB & WB CURB LANES CLOSED FROM LORNE AVE TO SPADINA CRES W
(Bridge washing & sealing)
Start: August 22, 8:00 p.m. End: August 23, 6:00 a.m.
VALLEY RD EB MEDIAN & CURB LANES REDUCED AT CIRCLE DR S
(Crash cushion repair)
Start: August 22, 7:00 p.m. End: August 23, 6:00 a.m.
CIRCLE DR W NB CURB LANE CLOSED FROM 19TH ST W TO 20TH ST W
(Crash cushion repair)
Start: August 22, 7:00 p.m. End: August 23, 6:00 a.m.
ONGOING
WANUSKEWIN RD SB CURB LANE CLOSED FROM 72ND ST E TO 71ST ST E
(Road work)
Start: August 14, 7:00 a.m. End: August 23, 4:30 p.m.
3RD AVE S SB LANES CLOSED FROM 21ST ST E TO 20TH ST E
(Connection repairs)
Two-way traffic will be maintained in NB lanes
Start: August 22, 7:00 a.m. End: August 24, 6:00 p.m.
CENTRAL AVE NB CURB LANE CLOSED FROM ROSSMO RD TO ATTRIDGE DR
(Shelterbelt removal)
Start: August 21, 9:00 a.m. End: August 25, 3:00 p.m.
BUTE ST ROAD CLOSED FROM WILLIAM AVE TO HANOVER AVE
(Weaver Park upgrades)
Broadway Ave intersection closed at Brute St.
Start: July 25, 7:00 a.m. End: August 31, 4:30 p.m.
SPADINA CRES E INTERSECTION CLOSED AT 22ND ST E
(Infrastructure upgrades)
Start: August 14, 7:00 a.m. End: September 7, 5:00 p.m.
MELVILLE ST INTERSECTION CLOSED AT JASPER AVE
(Infrastructure upgrades)
Start: August 8, 7:00 a.m. End: September 15, 5:00 p.m.
NEAULT RD ROAD CLOSED FROM 22ND ST W TO WHELAN RD
(Construction)
Start: July 24, 7:00 a.m. End: September 24, 6:00 p.m.
CLARENCE AVE N NB CURB LANE CLOSED FROM AIRD ST TO OSLER ST
(Contractor works)
Start: July 21, 7:00 a.m. End: September 29, 6:00 p.m.
CIRCLE DR E EB LANES CLOSED FROM WARMAN RD TO PRESTON AVE N
(Bridge rehabilitation)
Two-way traffic will be maintained in the WB lanes.
Start: June 25, 5:00 a.m. End: November 1, 5:00 p.m
All restrictions will be lifted as indicated, weather permitting and barring any unforeseen circumstances.
For more information about current road restrictions and construction, visit saskatoon.ca/construction.